Solar thermal re-engineering for Can Ricart sport centre

CLIENT: INSTITUT BARCELONA ESPORTS
LOCATION: BARCELONA
DATE: 2013

Arkenova carried out corrective actions that were detected during the audit in 2012 about the condition of the solar thermal system in this sport centre.

These actions resulted in a cost of approximately 20.000€ which was amortised in less than 2 years thanks to the savings in DHW.

Monitoring and maintenance are also carried out by Arkenova and managed by TERSA (waste treatment and management company).

The control of the installation is done by means of an equipment from RESOL DELTASOL MX and the monitoring is carried through the IoT platform SmartDataSystem.

The annual average coverage is in the range of 35-40 per cent, over the annual average consumption of 7.500 m3 of DHW.